On-load Tap Changers

Locations: Main Substation of Morning District
Project Type: On-load Tap Changers

As part of the preventive and corrective maintenance work of critical electrical infrastructure, the maintenance of the switches under load was carried out in the Main Substation of the District of Manhiça. The aim of this project was to ensure the operational reliability of power transformers, ensuring automatic voltage adjustment according to load variation in the distribution network.

02